What is left standing in the way of The George Hotel and Residences development? “There is still lots to do.”
Continue readingGospel Rock development has serious ground issues
Geotechnical report: earthworks done so far on Block 7 have to be redone; problems can be observed from Chaster Road
Continue readingGospel Rock developer has problem paying bills
Two companies, one of them local, put lien on title; developer had $2 million mortgage on Block 7 in 2019
Continue readingWho is the real contractor on Gospel Rock?
Web of construction companies with the same director have been sued seven times in three years in Vancouver law courts
Continue readingMachado’s expense account: what is the town hiding?
Cao’s financial records for 2018 and 2019 have been withheld; his expense receipts for 2012-2017 show an abundance of travel
Continue readingA binding requirement to build the George Hotel and Resort never existed
Lawyer retained by Coast Clarion says covenant between town and developer has no timeline, no penalties, and cannot be enforced
Continue readingWhen will shovels go in the ground on Gospel Rock?
Excavation starts next month; construction of a road to Shaw may start earlier than originally planned; 25 units are sold
Continue readingTown gives developer two-year permit extension for The George
Developer will give right-of-way through property until 2022 and work on new pathway if the project would not go ahead
Continue readingA tale of two empty inns on the Coast
Why are the Bella Beach Inn in Davis Bay and the former Ritz Inn in Lower Gibsons not being used?
Continue readingWill your house be safe from flooding in 2050? Check here
Independent organization of scientists and science reporters has produced a map of areas on the Coast likely to be flooded
Continue reading